Construction of Charlies Carwash

The commercial construction project for a tunnel carwash named “Charlies” began with high expectations and a meticulously planned schedule. This project involved the creation of a new, large tunnel carwash facility, designed to offer top-of-the-line carwash services with the latest technology.

Excavation and Unforeseen Challenges

During the excavation stage, our team encountered an unexpected challenge that had the potential to derail the entire project. It was discovered that the site sat atop an old landfill, a detail that had been overlooked in all the preliminary soil reports. This revelation necessitated immediate action and careful consideration to ensure the project’s continuation.

Initial Response and Actions

Upon discovering the landfill, the owner was promptly notified, and an urgent onsite meeting was arranged. It was clear that to proceed, significant modifications to the excavation plan were required. Our team determined that over-excavating the site to a depth of 17 feet would be essential to remove the unsuitable material.

Over-Excavation and Remediation

The process of over-excavation involved removing the existing landfill material within the building’s footprint. This task was performed with precision and care to avoid further complications. Once the over-excavation was complete, the next step involved importing engineered backfill. The imported material was then compacted according to the engineer’s specifications, ensuring a stable foundation for the carwash structure.

Impact on Project Schedule

The unforeseen landfill issue and the subsequent over-excavation and backfilling process introduced an initial delay of six weeks from the original project schedule. This delay posed a significant challenge, as it threatened to extend the project’s timeline and increase costs.

Strategic Planning and Scheduling

In response to the delay, our project management team re-evaluated the entire construction schedule. Through strategic planning, we optimized subcontractor schedules and coordinated material deliveries to expedite construction activities. This proactive approach ensured that no further delays would impede the progress of the project.

Successful Mitigation and Project Completion

Despite the initial setback, our team’s diligent efforts and effective management enabled us to make up for the lost time. By leveraging efficient scheduling and maintaining clear communication with all stakeholders, we successfully brought the project back on track.

Achieving the Original Schedule

Through meticulous scheduling and coordination, we managed to adhere to the original project timeline. The construction of Charlies Tunnel Carwash was completed as planned, demonstrating our ability to overcome unforeseen challenges and deliver quality results.

Conclusion

The construction of Charlies Tunnel Carwash serves as a testament to our team’s resilience and capability in handling unexpected obstacles. By swiftly addressing the landfill discovery, implementing an over-excavation and backfill strategy, and efficiently managing the project schedule, we achieved successful project completion without compromising on quality or timelines. This case study highlights the importance of adaptability and strategic planning in commercial construction projects.